Published On: Mon, Mar 14th, 2011

Proposed Power Projects in Bihar

New Projects

To help improve power generation capability, some new projects are already being processed by the Bihar State Electricity Boards. They are as follows -

 

Proposed Power Projects in Bihar

 

I. State Sector/Joint Venture

 

Ø     Barauni TPS Extension – Distt: Begusarai.

  • Under BSEB
    • 2 x 250 MW Extension at Barauni TPS
    • DPR prepared by M/s DCPL, Kolkata, Estimated Cost- Rs. 3066 Crores based at prices   in Jan-Mar 2009 excluding cost of Land.
    • Additional Land requirement- 615.37 acres. Present estimated cost Rs. 67.05 crores. Rs. 38.54 Crores has been deposited with concerned DM for acquisition of about 355 acres.
    • MoP has recommended MoC in August 2010 for allocation of Coal for 12th Plan.
    • Coal requirement – 2.65MMTPA. Processing fee of Rs. 5.00 lakh submitted to Ministry of Coal by BSEB vide letter no. 682 dated 27.06.06 for coal linkage. Probable Coal linkage from Rajmahal coal field or Urma Pahari Tola. Firm Coal linkage still awaited.
    • BHEL to implement BTG package (Boiler-Turbine-Generator) as OEM (Original Equipment Manufacturer). Techno-commercial offer will be submitted by BHEL shortly.
    • BPIC – JV of GoB, BSEB & ILFS is BSEB’s consultant for carrying out Pre award project development activity for setting up 2 x 250 MW Extension project at BTPS.
    • State Plan outlay amounting to Rs. 180 Crores has been released in the FY 2009-10.
    • M/s DESEIN appointed as Technical consultant for prepration of technical specifications of  BOP Package. Appointment of single BOP EPC Packages by M/s Desein though bidding process is in progress.
    • M/s BARSYL appointed as Technical consultant for development of Rail infrastructure at BTPS.
    • M/s Bhagawathi Anna Lab Ltd, Hyderabad appointed as Environmental consultant for EIA study and obtaining Final Environmental clearance from MoEF, New-Delhi
    • NOC from Airport Authority of India has been obtained for Chimney height 275 mtrs.
    • Water requirement for consumptive use to be met from river Ganga. Water Resources Dept., GoB has accorded clearance for 60 Cusecs for BTPS units (Existing & Extension units) and approval from CWC is accorded for 45 Cusec.
    • Ganga Water Scheme: M/S WAPCOS is consultant for preparation of DPR. Draft DPR submitted. Final DPR could not be submitted by M/s WAPCOS as clearance from Railway is yet to be obtained.
    • Expected schedule of Commissioning – 1st Unit synchronization in June ‘2014, 2nd Unit after 4 months of synchronization of 1stUnit.
    • 100 % power generated to be utilized by BIHAR/BSEB

Ø     Muzaffarpur TPS Extension – Distt:  Muzaffarpur

  • Under KBUNL (Kanti Bijlee Utpadan Nigam Ltd.- JV of BSEB & NTPC Ltd.)
  • 2×195 MW Extension at Muzaffarpur TPS
  • Unit size reduced from 250 MW to 195 MW as per aviation clearance of chimney height to 146.5 mtrs accorded by from Airport Authority of India on 16.07.2008.
  • FR prepared and approved by Company board in May 2009.
  • Estimated cost – Rs 3154.332 Crores
  • Coal linkage accorded for 2.92 MMTPA from ECL by Min. of Coal in Dec’08.
  • NTPC Ltd. is consultant.
  • Budget for equity share of BSEB for FY 2010-11 is Rs. 166 Crore.
  • State Plan Outlay for 2010-11- Rs. 129.28 Crore released to BSEB.
  • BSEB has released Rs. 78.849 Crore for 2010-11 as Equity Share to KBUNL.
  • LOA awarded to BHEL for main plant package on 28.04.2010.
  • Cotract agreement for BTG package signed with BHEL on 06.05.2010.
  • Water Resources Dept., GoB has given consent for 45 Cusecs from River Burhi Gandak. CWC has given clearance on 19.02.2010.
  • 85% generated power to Bihar/BSEB. PPA signed in Jan’10.
  • Kick-off meeting held on 24.05.2010
  • Expected Schedue of Commissioning –2012-13.

Ø     Nabinagar Super  TPP – Dist.: Aurangabad

  • Under NPGCPL (Nabinagar Power Generating Co. Pvt. Ltd.- JV of BSEB & NTPC Ltd)
  • 3×660 MW at Nabinagar and Barun blocks
  • FR prepared and approved by NPGCPL board
  • Estimated cost – 12759.879 Crores (Revised in July 2010).
  • NTPC Ltd is consultant. Estimated cost for consultancy Rs.120 crores.
  • Land area approx. 2832 acres for the project demarcated. Land cost estimated Rs.173 Crores (approx.) has been deposited to District Administration. 1871 acres Land acquired & remaining Land acquisition is under progress.
  • The topographical survey and geotechnical survey has been completed.
  • Water Resources Dept., GoB has given consent for drawl of water from Indrapuri Barrage on River Sone. CWC clearance accorded on 11.08.2010 for utilization of 125 Cusecs of Sone water as per Banasagar Agreement, 1973.
  • State Plan outlay amounting to Rs. 128 Crore for year 2009-10 for the equity share of BSEB in NPGC has been released.
  • Budget estimate for FY 2010-11- Rs. 324 Crores.
  • State Plan outlay for equity share of BSEB of Rs. 150 Crore for year 2010-11 has been released  to BSEB. Rs. 50 Crores released to M/s NPGC.
  • Various Statutory clearance have been/are being obtained.
  • Coal requirement 11.25 MMTPA. Coal linkage accorded in Mar 2010 by Min. of Coal from North Karanpura Coalfields.
  • PPA signed in Jan 2010 for 75% of generated power for BSEB.
  • Expected schedule of commissioning – 12th Plan (2015-16).

II. IPP Power Stations under Case-II Tariff Based Bidding

(85% of Power to be procured by BSEB, 15% of Power to be procured by Haryana, Rajasthan & Assam in order to avail the benefits under Mega Power Policy)

 

Ø     Buxar Bijlee Company Pvt. Ltd. – Dist: Buxar.

(Buxar Thermal Power Station at Chausa, Dist-Buxar)

  • Being processed by BPIC (Bihar Power Infrastructure Co.) – SPV promoted by Govt. of Bihar/BSEB and IL&FS, New Delhi.
  • 2×660 MW at Chausa, Dist-Buxar
  • Estimated cost- Rs. 6791.37 Crores (approximately)
  • Expected date of Commissioning –12th Plan, (2015-16)
  • SIPB approval received vide letter 163 dated 27.02.09.
  • Demarcation of land 1167 acres done. Land Acquisition is under process through Industrial Development Authority (IDA), Bihar. Section 4 notification to be issued shortly.
  • MoP has recommended MoC in August 2010 for allocation of Coal for 12th Plan.
  • Coal requirement – 6.25 MMTPA. The processing fee of Rs. 5.00 lakh deposited by BSEB vide letter no 745 dated 03.09.2008.
  • Water Resources Dept., GoB has given consent for 55 Cusec from River Ganga. CWC clearance accorded on 24.09.2010.
  • Terms of Reference (TOR) & site of TPP approved by Ministry of Environment & Forests, EIA report is completed & public hearing conducted on 30.07.2010.
  • Clearance for Chimney Height obtained from Airport Authority of India.
  • Detailed Topographical Survey & Geotechnical Investigations completed.
  • DPR prepared by M/s Fitchner Consulting Engineers Pvt. Ltd. & submitted to MoP & CEA.
  • CEA Site Selection Team visited proposed site in mid February 2010.Clarification sought by CEA on 10.05.2010 have been furnished on 17.05.2010. Report awaited.
  • CEA vide letter dated 21.07.2010 asked details/informations regarding project for pre-qualification and prioritization for 12thPlan Thermal Power Projects. Details as per format furnished on 03.08.2010.

Ø     Lakhisarai Bijlee Company Pvt. Ltd. – Dist: Lakhisarai.

Lakhisarai Thermal Power Station at Kajara, Dist-Lakhisarai.)

  • Being processed by BPIC (Bihar Power Infrastructure Co.)-SPV promoted by Govt. of Bihar/BSEB and IL&FS, New Delhi.
  • 2×660 MW at Kajara, Dist-Lakhisarai
  • Estimated cost- Rs. 6810.10 Crores (approximately)
  • Expected date of Commissioning – 12th Plan, (2015-16)
  • SIPB approval received vide letter 162 dated 27.02.09.
  • Demarcation of land 1165 acres done. Land Acquisition is under process through Industrial Development Authority (IDA), Bihar. Section 4 notification to be issued shortly.
  • Coal requirement- 6.25 MMTPA. The processing fee of Rs. 5.00 lakh deposited by BSEB vide letter no 745 dated 03.09.2008.
  • Water Resources Dept., GoB has given consent for 55 Cusec from River Ganga. CWC clearance accorded on 15.09.2010.
  • Terms of Reference (TOR) & site of TPP approved by Ministry of Environment & Forests, EIA report is completed & public hearing conducted on 25.07.2010.
  • Clearance for Chimney Height obtained from Airport Authority of India.
  • Detailed Topographical Survey & Geotechnical Investigations completed.
  • DPR prepared by M/s Fitchner Consulting Engineers & submitted to MoP & CEA.
  • CEA Site Selection Team visited proposed site in mid February 2010. Clarification sought by CEA on 10.05.2010 have been furnished on 17.05.2010. Report awaited.
  • CEA vide letter dated 21.07.2010asked details/informations regarding project for pre-qualification and prioritization for 12th Plan Thermal Power Projects. Details as per format furnished on 03.08.2010.

Ø     Pirpainti Bijlee Company Pvt. Ltd. – Dist: Bhagalpur.

(Pirpainti Thermal Power Station at Pirpainti, Dist-Bhagalpur.)

  • Being processed by BPIC (Bihar Power Infrastructure Co.) – SPV promoted by Govt. of Bihar/BSEB and IL&FS, New Delhi.
  • 2×660 MW at Pirpainti, Dist-Bhagalpur
  • Estimated cost- Rs. 6820.50 Crores (approximately)
  • Expected date of Commissioning – 12th Plan, (2015-16)
  • Demarcation of land 1171 acres done. Land Acquisition is under process through Industrial Development Authority (IDA), Bihar. Section 4 notification to be issued shortly.
  • Coal requirement- 6.25 MMTPA. The processing fee of Rs. 5.00 lakh deposited by BSEB vide letter no  682 dated 27.06.2006.
  • Water Resources Dept., GoB has given consent for 55 Cusec from River Ganga. CWC clearance accorded on 16.09.2010.
  • Terms of Reference (TOR) & site of TPP approved by Ministry of Environment & Forests, EIA report is completed & public hearing conducted on 24.07.2010.
  • Clearance for Chimney Height obtained from Airport Authority of India.
  • Detailed Topographical Survey & Geotechnical Investigations completed.
  • DPR prepared by M/s Fitchner Consulting Engineers & submitted to MoP & CEA.
  • CEA Site Selection Team visited proposed site in mid February 2010. Clarification sought by CEA on 10.05.2010 have been furnished on 17.05.2010. Report awaited.
  • CEA vide letter dated 21.07.2010asked details/informations regarding project for pre-qualification and prioritization for 12th Plan Thermal Power Projects. Details as per format furnished on 03.08.2010.

III. IPP Power Stations (MOU signed with BSEB)

 

Ø     M/s Jas Infrastructure Capital Pvt Ltd, Nagpur at Dist.: Banka

  • MoU with BSEB signed on 17th Oct’2007. Addendum to MoU signed on 29.12.2008 for enhancing the ultimate capacity to 2640 MW and extending MoU for thirteen months. Again MoU signed for next 13 months i.e. upto Feb 2011. BSEB has right to purchase 25% of power from the proposed project.
  • 4×660 MW at Siriya, Gidhasimer, Bhalki and Gokula in Block- Bhaunsi, in Banka district.
  • Estimated cost- Rs. 11120 Crores.
  • Developer has requested to addendum in capacity from 4X660 MW to 6X660 MW.
  • 1050 acres land has been identified and its acquisition is in process. Registration of the land has started and till date approx. 790 acres of land has already been registered through private negotiations and ~260 acres land are in under process. Area fencing work has been initiated at site.
  • Full fledged office with all required infrastructure and guest house is functional at Bounsi.
  • Mahuagarhi coal block allotted by MoC on 50:50 JV basis between JICPL & CESC. Coal quantity estimated for 1000 MW power generation. Applied for Long Term Coal Linkage for full requirement to MOC,GOI.
  • Water linkage obtained from Water Resources Dept, GoB  gave consent for 85 Cusec from Chandan Dam. Route survey is being carried out by M/s S and S Associates.
  • Pre- feasibility Report for the Power Plant prepared and submitted.
  • ToR finalized by MoEF, Environmental & Socio-Economic data collection completed. EIA-EMP Studies & Public Hearing completed. Forest clearance not applicable.
  • Airport Authority of India has issued NOC for construction of 275m high chimney in April’2009.
  • Detail Power Evacuation Study has been done by PRDC – Bangalore. For power evacuation applied to PGCIL for the open access under long term connectivity on 23.06.2009.
  • Approval for Private Railway siding is granted.
  • M/s Fichtner Consulting Engineers (India) Pvt. Ltd. is consultant for the Project.
  • Project Feasibility Report & DPR have been prepared.
  • Geotechnical investigations have been conducted based on the final plot plan for the project. Land development plans are being finalized.
  • Expected schedule of commissioning – 12th Plan

Ø     M/s Nalanda Power Company Ltd, Kolkata at Dist.: Bhagalpur

  • MoU signed on 3rd July 2008. Validity of MoU extended upto 02.10.2011. BSEB has right to purchase 25% of power from the proposed project.
  • 4×500 MW (in two phases) at south Pirpainti, Dist.: Bhagalpur
  • Estimated Cost : Rs. 9260 Crores excluding IDC
  • Coal requirement: 5.24 MMTPA for 2X500 MW (Phase-I)
  • Pre-feasibility Report prepared. DPR will be prepared after coal linkage.
  • Land requirement 878 acres (2 Phases) at Khidirpur, Choudhary Basantpur, Laxmipur, Bijoram Chawk, Shadipur, Hiranand, Govindpur at Pirpainti South, Bhagalpur district. 404 acres of land identified for the main plant area. NOC received from District Collector for setting up the power station in the identified land vide letter no. 1465 dated 09.07.09.
  • MoEF accorded Prior Clearance for the site vide letter dt 10.02.09.
  • Formal application with requisite fee made to Ministry of coal for long term coal linkage on 26.07.08. Coal linkage still awaited.
  • MECON has completed EIA Study based on ToR approved by MoEF. Public hearing to be conducted shortly.
  • Water Resources Dept, GoB has approved drawal of 80 Cusec of consumptive water from River Ganga on 21.10.2008. CWC has approved that 80 cusecs of water provided for the project is out of the water available in Eastern Kosi Canal System within its present utilization.
  • NOC obtained from Airport Authority of India in April’2009 for construction of Chimney.
  • Railway siding study conducted for connectivity.
  • Power Evacuation- Applied to PGCIL on 13.02.2009.
  • Expected schedule of commissioning – 12th Plan.

Ø     M/s Ganga Power & Natural Resources Ltd, Kolkata at Dist.: Bhagalpur

Formerly: Adhunik Power & Natural Resources Ltd, Kolkata)

  • Name change accorded in SIPB on 29.06.2010.
  • New MoU with BSEB signed on 29th Nov’2010 for 1320MW in the name of GPNRL for 13 (thirteen) months.
  • MoU was signed with BSEB on 19th Oct’2008 for 1000MW. Validity extended upto 19th Dec’2010.
  • Capacity change to 2×660 MW (1320 MW) accorded on 01.02.2010 by GoB. BSEB has right to purchase 25% of power from the proposed project.
  • Coal requirement- 6.9 MMTPA.
  • Estimated Cost : Rs. 7500 Crores
  • BIADA has allotted 300 acres land. At villages Gobindpur, Rajganj, Jairam Bandhu, Roshanpur, Meharpur in Pirpainti block Dist.: Bhagalpur Application for acquisition of 815 acres land in Pirpainti block given to GoB.
  • Applied for aviation clearance for construction of 275 mtrs Chimney.
  • 60 MCM water has been allocated from River Ganga by WRD, GoB. CWC Clearance accorded on 17.09.2010. Water study for availability completed.
  • Pre-feasibility report submitted to MoEF.
  • Processing fee of Rs. 5.00 Lakh for allocation of coal deposited by the firm vide their letter no AG/AAAPL/890 dated 01.09.09 to Ministry of Coal.GoB requested MoP, GoI for grant of long term coal linkage in December 2010.
  • M/s Fitchner has been appointed as engineering consultants for the TPP, who has finalized the tentative plot plan and bankable DPR. Specification for BTG packages also prepared.
  • Expected schedule of commissioning – 12th Plan.

M/s India Power Corporation Ltd, Kolkata

  • Revised capacity proposed in March 2010 – 2X660 MW.
  • MoU signed on 03.09.2010 for a validity of 13 (Thirteen) months.
  • 1500 acres of land identified at Indragachhi, Sangrampur, Block- Areraj in East Champaran district. Acquisition process to start after obtaining Cabinat approval.
  • Estimated Cost : Rs. 7280 Crores
  • Coal requirement – 6.20 MMTPA
  • Water requirement 62 Cusecs (Approx.) permitted to draw from River Gandak from WRD, GoB in June 2010.
  • Tendering for SG&STG Package is expected in April 2011.
  • 25% ex-bus generation (300 MW approx.) to be allotted to Bihar State.
  • Approval accorded by SIPB in its 53rd meeting dated 02.01.08
  • Feasibility Report submitted by the firm in April 2010.
  • Expected schedule of commissioning- 2014-15.

M/s AES India Pvt. Ltd, Gurgaon

  • 2 x 660 MW, Coal Based Thermal Power Project at Jagdishpur in dist. Bhagalpur..
  • Approval accorded by SIPB in its 89th meeting dated 11.08.010
  • MoU signed on 02.12.2010 for a validity of 13 (Thirteen) months.
  • Land required- 1500 acres. (as per MoU)
  • Coal requirement 8.00 MMTPA
  • Water requirement 42 MCM from River Ganga which is 15-20 KM distant from proposed site.
  • Total investment- Rs. 8120 Crores.
  • BSEB shall have the first right to claim to purchase / refusal of power up to 25 % maximum from the proposed power plant.
  • Expected Date of Production- 31.03.2016

M/s MIRACH Power Pvt. Ltd, Gurgaon

  • 2 x 660 MW Coal Fired Thermal Power Project at Lakhisarai distt.
  • Approval accorded by SIPB in its 89th meeting dated 11.08.010
  • MoU signed on 16.11.2010 for a validity of 13 (Thirteen) months.
  • Water requirement 40 Cusecs (Approx.) permitted to draw from River Ganga from WRD, GoB in September 2010.
  • BSEB shall have the first right to claim to purchase / refusal of power up to 25 % maximum from the proposed power plant.
  • Total investment- Rs.7360 Crores.
  • Land required- 1000 acres.

IV. Other IPP projects approved by State Investment Planning Board (SIPB)

M/s Subhas Projects & Marketing Ltd, Kolkata

  • 1200 MW at Dist. Lakhisarai.
  • Approval accorded by SIPB in its 53rd meeting dated 02.01.08
  • Progress has not been reported by the firm

M/s Cement Manufacturing Company Ltd., Kolkata,

  • 500 MW at Kahalgaon Dist.: Bhagalpur.
  • Approval accorded by SIPB in its meeting dated 26.03.07.
  • 600 acres of land identified at Kahalgaon, Dist- Bhagalpur.
  • Application submitted to MoC for Coal Block allocation.
  • Progress has not been reported by firm.

M/s Essar Power, Ranchi

  • 1800 MW at Pirpainti, Bhagalpur.
  • Approval accorded by SIPB in its 61st meeting dated 29.09.08.
  • Progress has not been reported by the firm

M/s Usha Martin, New Delhi

  • 1200-1320 MW at Meherpur in Pirpainti Block, Bhagalpur.
  • Estimated Cost : Rs. 6000 Crores
  • Approval accorded by SIPB in its 66th meeting dated 29.06.09.
  • Pre-Feasibility Report submitted to SIPB.
  • 1200 acres of Land required.
  • Coal requirement – 6.50 MMTPA for 1200 MW capacity or 7 MMTPA capacity for 1320MW. Requires a captive coal block with reserves of 350-400 MT.
  • 5300 M3/Hr of Water for Industrial use for the project from River Ganga by WRD, GoB.
  • Progress has not been reported by the firm

M/s East-West Power Generation Co. Ltd., Maharastra

  • 1000 MW at Kahalgaon, Bhagalpur.
  • Approval accorded by SIPB in its 62nd meeting dated 18.11.08.
  • PFR prepared and submitted to Industry Deptt. GoB.
  • Progress has not been reported by the firm

M/s Triton Energy Ltd.,Gurgaon, Haryana,

  • 1320 MW at Village- Kochar, Block- Barun, Dist : Aurangabad
  • Coal Requirement – 6.65 MMTPA
  • Pre-feasibility report has been prepared and submitted to SIPB, BSEB & Dept. of Energy.
  • 1400 acres land identified in Kochar village at Barun block, Dist.: Aurangabad, Bihar.
  • Application has been made for acquisition of identified land to GoB.
  • Negotiation with consultant for conducting EIA is in advance stage.
  • Application made to WRD, GoB for withdrawal of 52.8cusecs water from River Sone.
  • Progress has not been reported by the firm.

M/s Krishak Bharti Co-operative Ltd, New Delhi

  • 1320 MW
  • Approval Accorded by SIPB in its meeting dated 17.03.08
  • Firm has proposed to establish a power project at Chausa (Dist- Buxar), one of the three sites identified by BPICPL through MOU route.
  • Proposal is under active consideration of GoB.

M/s Arrissan Power Limited, Kolkata

  • 2 X 660 MW Coal Based Thermal Power Plant.
  • At Prabhawati Nagar in Banka District of Bihar.
  • Approval accorded by SIPB in its meeting dated 24.05.2010.
  • Application made to WRD, GoB for withdrawal of Water.
  • Estimated investment around Rs. 7260 Crores.

M/s Global Powmin, Ranchi

  • 4 x 660 MW,  Coal Based Thermal Power Project.
  • Approval accorded by SIPB in its 86th meeting on dated 08.06.2010
  • At Sirdala dist. Nawada in Bihar State.
  • Land requirement- 2200 acres.
  • Estimated cost- Rs. 11000 Crores.
  • Expected date of commissioning- Jan-2014.

Nuclear Power Project

 

NPCIL proposed for installation of 4×700 MW Nuclear Power Plant at Rajauli, Dist. Nawadah.

23,000 hectare-meter (320 cusecs) quantity of water is required, of which 14016 hectare-meter (160 cusec) would be consumptive. Water Resources Dept., GoB indicated adequate quantity of water not available from proposed Dhanarjay reservoir and existing Phulwaria reservoir for plant of 4×700 MW. Water Resources Dept., GoB indicated availability of 12785 cubic meters per hour (127 cusecs) water to meet requirement of 2×700 MW or 4X450 MW. NPCIL has been requested to process with regard to expected availability of water.

 

 

 

  • http://www.jakson.com santosh

    contact for cummins genset

    • admin

      Jaction, thanks

      BiharPrabha is doing a lot of market research on power sector which is so important for economic development of Bihar. We are adding more and more information on power sector exclusively in respect state of Bihar & in fact this site is dedicated to the people of Bihar.

      Cummins is well known brand in DG captive power sector. But U should also market solar products. BiharPrabha can help U. This will protect environment also.

      BiharPrabha

  • http://www.sherman-india.com Dipti Munshi

    We appreciate BiharPrabha’s sincere research effort before publishing authentic power sector news on their website. We will continue surfing your website to analyze Bihar’s progress in power sector.

    Good to see Bihar progressing.

    • Biharprabha Admin

      Dipti jee

      Thanks for comments. We will continue our efforts.

      Bihar Prabha

  • http://azafar.com zafar imam

    really very great. the contribution is really fabulous in one word. in every terms of information it has a qualitative edge, which gives worth for reading.

    great job being done.

    • Biharprabha Admin

      Jafar Jee
      Thanks for comments. Such things
      encourages us. Happy Dipawali

      BiharPrabha

  • Aditya Agarwal

    Dear Bihar Prabha,

    I am looking forward for setup of Power plant for new upcoming industry in Bihar.
    I will even plant an water treatment plant setup as a common effluent plant.
    Will like to know how we can work and join your hand to grow.

    Regards
    Aditya
    9543755577

    • Biharprabha Admin

      Dear Aditya
      We are not clear. “setting up Power plant for new upcoming industry in Bihar. I will even plant an water treatment plant setup as a common effluent plant.”
      Please write in detail about your proposal
      BiharPrabha

Associated Topics